Power up check list
Overview
After a building power down, follow these steps to ensure the security system is fully operational.
-
Verify System Functionality:
- Do not leave the building without confirming with the building management that the system is up and running.
-
Controller Check:
- Use the controller floor diagnostic to see if all controllers are online.
- Select each controller individually and click "Controller Info" to verify their status.
- Ensure no controllers are down by unchecking "Show Only Online Controllers".
-
Full System Check:
- Contact BluCare to obtain a full list of online and used controllers.
- Perform a simulated swipe; if successful, try a normal swipe.
-
Problem Resolution:
- Address any issues discovered. If unsure how to investigate, call the support line:
- Regular support line or emergency line based on the time.
- Emergency line (available 24/7): 1-844-425-8209, Option 6.
- Address any issues discovered. If unsure how to investigate, call the support line:
-
Starting Points:
- Verify all Access Controllers are powered up and online in BluB0X.
- Check if credential reads are displayed in Events and Events History for every controller.
- Ensure NVRs are powered up and communicating with BluSKY; contact BluCare for a list of online/offline cameras.
- Verify all cameras are online (get a list of cameras online/offline before powering down).
- Confirm alarms are working.
- Ensure Interactive Maps are functioning.
- Verify all person readers are communicating with BluSKY.
- Check if PR facial recognition and physical credentials are working; if not, call support.
- Confirm intercoms are working and calling the master station.
- Ensure power controllers are online and showing M8 data.
- Verify DDE primary and secondary are online and local sync is running.
- Ensure elevator requests are operational.
When to Use This Checklist
- Use this checklist after powering down a building to ensure all systems are operational.