Information Technology Statement of Intent

Policy Statement

Objectives

Key Personnel Contact Info. 

Notification Calling Tree

External Contacts. 

External Contacts Calling Tree. 

1      Plan Overview

1.1       Plan Updating

1.2       Plan Documentation Storage

1.3       Backup Strategy

1.4       Risk Management

 

2      Emergency Response

2.1       Alert, escalation and plan invocation. 9

2.1.1    Plan Triggering Events. 9

2.1.2    Assembly Points 10

2.1.3    Activation of Emergency Response Team.. 10

2.2       Disaster Recovery Team.. 10

2.3       Emergency Alert, Escalation and DRP Activation. 10

2.3.1    Emergency Alert 11

2.3.2    DR Procedures for Management 11

2.3.3    Contact with Employees 11

2.3.4    Backup Staff 11

2.3.5    Recorded Messages / Updates 12

2.3.7    Alternate Recovery Facilities / Hot Site. 12

2.3.8    Personnel and Family Notification. 12

 

3      Media. 12

3.1       Media Contact

3.2       Media Strategies

3.3       Media Team

3.4       Rules for Dealing with Media

 

4      Insurance

 

5      Financial and Legal Issues

5.1       Financial Assessment 

5.2       Financial Requirements

5.3       Legal Actions

 

6      DRP Exercising

 

Appendix A – Technology Disaster Recovery Plan Templates

Disaster Recovery Plan for <System One>

Disaster Recovery Plan for <System Two>

Disaster Recovery Plan for Local Area Network (LAN) 

Disaster Recovery Plan for Wide Area Network (WAN)

Disaster Recovery Plan for Remote Connectivity

Disaster Recovery Plan for Voice Communications

Appendix B – Suggested Forms 22

Damage Assessment Form 22

Management of DR Activities Form 22

Disaster Recovery Event Recording Form 23

Disaster Recovery Activity Report Form 23

Mobilizing the Disaster Recovery Team Form 24

Mobilizing the Business Recovery Team Form 24

Monitoring Business Recovery Task Progress Form 25

Preparing the Business Recovery Report Form 25

Communications Form 26

Returning Recovered Business Operations to Business Unit Leadership 26

Business Process/Function Recovery Completion Form 27
 

Information Technology Statement of Intent

This document delineates our policies and procedures for technology disaster recovery, as well as our process-level plans for recovering critical technology platforms and the telecommunications infrastructure. This document summarizes our recommended procedures.  In the event of an actual emergency situation, modifications to this document may be made to ensure physical safety of our people, our systems, and our data.

Our mission is to ensure information system uptime, data integrity and availability, and business continuity.

Policy Statement

Corporate management has approved the following policy statement:

  • The company shall develop a comprehensive IT disaster recovery plan.
  • A formal risk assessment shall be undertaken to determine the requirements for the disaster recovery plan.
  • The disaster recovery plan should cover all essential and critical infrastructure elements, systems and networks, in accordance with key business activities.
  • The disaster recovery plan should be periodically tested in a simulated environment to ensure that it can be implemented in emergency situations and that the management and staff understand how it is to be executed.
  • All staff must be made aware of the disaster recovery plan and their own respective roles.
  • The disaster recovery plan is to be kept up to date to take into account changing circumstances.

Objectives

The principal objective of the disaster recovery program is to develop, test and document a well-structured and easily understood plan which will help the company recover as quickly and effectively as possible from an unforeseen disaster or emergency which interrupts information systems and business operations.  Additional objectives include the following:

•      The need to ensure that all employees fully understand their duties in implementing such a plan

•      The need to ensure that operational policies are adhered to within all planned activities

•      The need to ensure that proposed contingency arrangements are cost-effective

•      The need to consider implications on other company sites

•      Disaster recovery capabilities as applicable to key customers, vendors and others

Key Personnel Contact Info

 

Name, Title

Contact Option

Contact Number

Sean Dyer – Sr VP Engineering

Work

844-425-8209

 

Alternate

 

 

Mobile

603-508-0447

 

Home

603-329-7334

 

Email Address

sdyer@blub0x.com

 

Alternate Email

 

 

 

 

Patrick Barry - CEO

Work

844-425-8209

 

Alternate

 

 

Mobile

(917) 656-0526

 

Home

 

 

Email Address

pbarry@blub0x.com

 

Alternate Email

 

 

 

 

Patrick de Cavaignac - COO

Work

(844) 425-8209 ext.703

 

Alternate

 

 

Mobile

(914) 255-0025

 

Home

 

 

Email Address

patdecav@blub0x.com

 

Alternate Email

 

 

 

 

Simon Goldshmid – VP Engineering

Work

(844) 425-8209

 

Alternate

 

 

Mobile

781-883-3284

 

Home

 

 

Email Address

sgoldshmid@blub0x.com

 

Alternate Email

 

 

 

 

Robert Domings – Sr Engineer

Work

978-257-5186

 

Alternate

 

 

Mobile

978-257-5186

 

Home

978-609-7557

 

Email Address

bbrown@blub0x.com

 

Alternate Email

 

 

 

 

Shaun Peterson – Director Customer Support

Work

(844) 425-8209 Ext. 2

 

Alternate

 

 

Mobile

(978) 609-7557  

 

Home

 

 

Email Address

speterson@blub0x.com

 

Alternate Email

 

 

1.1    Plan Updating

 

It is necessary for the DRP updating process to be properly structured and controlled.  Whenever changes are made to the plan they are to be fully tested and appropriate amendments should be made to the training materials. This will involve the use of formalized change control procedures under the control of the IT Director or Sr VP Engineering.

 

1.2    Plan Documentation Storage

 

Copies of this Plan, CD, and hard copies will be stored in secure locations to be defined by the company.  Each member of senior management will be issued a CD and hard copy of this plan to be filed at home.  Each member of the Disaster Recovery Team and the Business Recovery Team will be issued a CD and hard copy of this plan.   A master protected copy will be stored on specific resources established for this purpose in the Engineering Sharepoint Site on Office 365. 

 

1.3    Backup Strategy

 

Key business processes and the agreed backup strategy for each are listed below.  The strategy chosen is for a fully mirrored recovery site at the company’s datacenter in California. This strategy entails the maintenance of a fully mirrored duplicate site which will enable instantaneous switching between the live site (headquarters) and the backup site.

 

 

KEY BUSINESS PROCESS

BACKUP STRATEGY

IT Operations

Fully mirrored recovery site

Tech Support - Hardware

Fully mirrored recovery site

Tech Support - Software

Fully mirrored recovery site

Facilities Management

Fully mirrored recovery site

Email

Fully mirrored recovery site

Purchasing

Fully mirrored recovery site

Disaster Recovery

Fully mirrored recovery site

Finance

Fully mirrored recovery site

Contracts Admin

Fully mirrored recovery site

Warehouse & Inventory

Fully mirrored recovery site

Product Sales

Fully mirrored recovery site

Maintenance Sales

Fully mirrored recovery site

Human Resources

Off-site data storage facility

Testing Fully Mirrored Recovery site -

Fully mirrored recovery site

Call Center

Fully mirrored recovery site

Web Site

Fully mirrored recovery site

 

1.4    Risk Management

There are many potential disruptive threats which can occur at any time and affect the normal business process. We have considered a wide range of potential threats and the results of our deliberations are included in this section.  Each potential environmental disaster or emergency situation has been examined. The focus here is on the level of business disruption which could arise from each type of disaster.

 

Potential disasters have been assessed as follows:

 

Potential Disaster

Probability Rating

Impact Rating

Brief Description Of Potential Consequences & Remedial Actions

Flood

1

3

All data and sourcecode is backed up in geo-redundant location.

Fire

1

3

All data and sourcecode is backed up in geo-redundant location.

Tornado

5

 

All data and sourcecode is backed up in geo-redundant location.

Electrical storms

5

 

All data and sourcecode is backed up in geo-redundant location.

Act of terrorism

5

 

May disrupt internet/communications

Act of sabotage

5

 

All data and sourcecode is backed up in geo-redundant location.

Electrical power

failure

3

4

This only affects people working from home as power failure usually means internet failure as well.

Loss of communications network services

4

4

Fully redundant network access at datacenter

 

Probability: 1=Very High, 5=Very Low             Impact: 1=Total destruction, 5=Minor annoyance

 

2.1.1  Plan Triggering Events

Key trigger issues at headquarters that would lead to activation of the DRP are:

•      Total loss of all communications

•      Partial or total loss of website functionality

•      Total loss of power

•      Flooding of the premises

•      Loss of the building

2.1.2 Assembly Points

Where the premises need to be evacuated, the DRP invocation plan identifies two evacuation assembly points:

•      Primary – Far end of main parking lot;

•      Alternate – Parking lot across the street

During off-hours, staff should remain at home and work remotely.  All email and phone services are provided as a service and will not be affected by the HQ building being physically unavailable.

2.1.3  Activation of Emergency Response Team

When an incident occurs the Emergency Response Team (ERT) must be activated.  The ERT will then decide the extent to which the DRP must be invoked.   All employees must be issued a Quick Reference card containing ERT contact details to be used in the event of a disaster.  Responsibilities of the ERT are to:

•      Respond immediately to a potential disaster and call emergency services;

•      Assess the extent of the disaster and its impact on the business, data center, etc.;

•      Decide which elements of the DR Plan should be activated;

•      Establish and manage disaster recovery team to maintain vital services and return to normal operation;

•      Ensure employees are notified and allocate responsibilities and activities as required.

2.2    Disaster Recovery Team

The team will be contacted and assembled by the ERT.  The team's responsibilities include:

•      Establish facilities for an emergency level of service within 2.0 business hours;

•      Restore key services within 4.0 business hours of the incident;

•      Recover to business as usual within 8.0 to 24.0 hours after the incident;

•      Coordinate activities with disaster recovery team, first responders, etc.

•      Report to the emergency response team.


2.3    Emergency Alert, Escalation and DRP Activation

This policy and procedure has been established to ensure that in the event of a disaster or crisis, personnel will have a clear understanding of who should be contacted.  Procedures have been addressed to ensure that communications can be quickly established while activating disaster recovery. 

The DR plan will rely principally on key members of management and staff who will provide the technical and management skills necessary to achieve a smooth technology and business recovery.  Suppliers of critical goods and services will continue to support recovery of business operations as the company returns to normal operating mode.  

2.3.1  Emergency Alert

The person discovering the incident calls a member of the Emergency Response Team in the order listed:

 

Emergency Response Team

• Shaun Peterson

• Sean Dyer

•Simon Goldshmid

 

If not available try:

• Robert Domings

• Patrick Barry

 

The Emergency Response Team (ERT) is responsible for activating the DRP for disasters identified in this plan, as well as in the event of any other occurrence that affects the company’s capability to perform normally. 

One of the tasks during the early stages of the emergency is to notify the Disaster Recovery Team (DRT) that an emergency has occurred. The notification will request DRT members to assemble at the site of the problem and will involve sufficient information to have this request effectively communicated. The Business Recovery Team (BRT) will consist of senior representatives from the main business departments. The BRT Leader will be a senior member of the company's management team, and will be responsible for taking overall charge of the process and ensuring that the company returns to normal working operations as early as possible.

2.3.2  DR Procedures for Management

Members of the management team will keep a hard copy of the names and contact numbers of each employee in their departments.  In addition, management team members will have a hard copy of the company’s disaster recovery and business continuity plans on file in their homes in the event that the headquarters building is inaccessible, unusable, or destroyed.

2.3.3  Contact with Employees

Managers will serve as the focal points for their departments, while designated employees will call other employees to discuss the crisis/disaster and the company’s immediate plans.  Employees who cannot reach staff on their call list are advised to call the staff member’s emergency contact to relay information on the disaster.

2.3.4  Backup Staff

If a manager or staff member designated to contact other staff members is unavailable or incapacitated, the designated backup staff member will perform notification duties.

2.3.5  Recorded Messages / Updates

For the latest information on the disaster and the organization’s response, staff members can call the main number listed in the DRP wallet card.  Included in messages will be data on the nature of the disaster, assembly sites, and updates on work resumption.

2.3.7  Alternate Recovery Facilities / Hot Site

If necessary, the hot site will be activated and notification will be given via recorded messages or through communications with managers.  Hot site staffing will consist of members of the disaster recovery team only for the first 24 hours, with other staff members joining at the hot site as necessary.  If a hot site is not required, team members may work from home using Skype, cell phones and internet connections.

2.3.8  Personnel and Family Notification

If the incident has resulted in a situation which would cause concern to an employee’s immediate family such as hospitalization of injured persons, it will be necessary to notify their immediate family members quickly.

 

3.1    Media Contact

Assigned staff will coordinate with the media, working according to guidelines that have been previously approved and issued for dealing with post-disaster communications.

 

3.2    Media Strategies

1.     Avoiding adverse publicity

2.     Take advantage of opportunities for useful publicity

3.     Have answers to the following basic questions:

·      What happened?

·      How did it happen?

·      What are you going to do about it?

 

3.3    Media Team

•      Jesica Trejo

•      Ed O’Callaghan

•      Patrick Barry

 

3.4     Rules for Dealing with Media

Only the media team is permitted direct contact with the media; anyone else contacted should refer callers or in-person media representatives to the media team.

 

5.1    Financial Assessment

 

The emergency response team shall prepare an initial assessment of the impact of the incident on the financial affairs of the company. The assessment should include:

  • Loss of financial documents
  • Loss of revenue
  • Theft of checkbooks, credit cards, etc.
  • Loss of cash

 

5.2    Financial Requirements

 

The immediate financial needs of the company must be addressed.  These can include:

  • Cash flow position
  • Temporary borrowing capability
  • Upcoming payments for taxes, payroll taxes, Social Security, etc.
  • Availability of company credit cards to pay for supplies and services required post-disaster

 

5.3    Legal Actions

 

The company legal department and ERT will jointly review the aftermath of the incident and decide whether there may be legal actions resulting from the event; in particular, the possibility of claims by or against the company for regulatory violations, etc.

 

6       DRP Exercising

 

Disaster recovery plan exercises are an essential part of the plan development process.  In a DRP exercise no one passes or fails; everyone who participates learns from exercises – what needs to be improved, and how the improvements can be implemented.  Plan exercising ensures that emergency teams are familiar with their assignments and, more importantly, are confident in their capabilities.

 

Successful DR plans launch into action smoothly and effectively when they are needed. This will only happen if everyone with a role to play in the plan has rehearsed the role one or more times.  The plan should also be validated by simulating the circumstances within which it must work and seeing what happens.

 

Disaster Recovery Plan for BluSKY DB

SYSTEM
 

 

OVERVIEW

 

PRODUCTION SERVER

Location: Azure East US

Server Model:  Unknown

Operating System:  Windows/Azure SQL

CPUs: 20

Memory: 64GB 

Total Disk: 2000GB

System Handle: 

System Serial #:

DNS Entry:  Redacted

IP Address:  Redacted

Other:

HOT SITE SERVER

Azure West US

APPLICATIONS

(Use bold for Hot Site)

SQL Server – hot mounted with real-time SQL replication from US East server

ASSOCIATED SERVERS

Redacted

 

KEY CONTACTS

 

Hardware Vendor

N/A

System Owners

N/A

Database Owner

Engineering – Sean Dyer, Simon Goldshmid, Robert Domings, Vadim Ivantsevich

Application Owners

Engineering – Sean Dyer, Simon Goldshmid, Robert Domings, Vadim Ivantsevich

Software Vendors

Microsoft

Offsite Storage

None

 

BACKUP STRATEGY FOR SYSTEM ONE

 

Daily

Azure Default Backup Strategy/Storage

Monthly

Azure Raw Storage

Quarterly

Azure Raw Storage

 

SYSTEM ONE
DISASTER RECOVERY PROCEDURE

 

 

Scenario 1

 

Total Loss of Data

 

Fail over to hot-backup site in Western US.

Perform rebuild of primary server in US East with backup and incrementals from Azure backups.  Add incrementals from new activity occurring in West server.  Fail back.

 

Scenario 2

 

Total Loss of HW

 

Fail over to hot-backup site in Western US.

Perform rebuild of primary server in US East by re-commissioning in Azure Portal.  Perform data restoration as above in Total Loss of Data.  Restore to Eastern US datacenter.

 

 

ADDENDUM

 

CONTACTS

 

Sean Dyer

sdyer@blub0x.com
603-508-0447

Simon Goldshmid

sgoldshmid@blub0x.com
781-883-3284

Robert Domings

bbrown@blub0x.com

Vadim Ivantsevich

vindigo@blub0x.com

 

File Systems 12-01-2017

File System as of 12-01-2017

 

Minimal file systems to be created and restored from backup:

 

 

 

Filesystem            kbytes       Used       Avail       %used         Mounted on

Database BluB0X   1300GB of 2000GB capacity

Database BluB0XLogs 65GB of 100GB capacity

Other critical files to modify

None

Necessary directories to create

N/A

Critical files to restore

Database files, as outlined in Complete Data Loss above

Secondary files to restore

None

Other files to restore

None

 

 

 

Disaster Recovery Plan for BluSKY Webservers

SYSTEM
 

 

OVERVIEW

 

PRODUCTION SERVER

Location: Azure US East datacenter

Server Model:  Default1 (Standard: 2 Large)

Operating System:  Windows 2019

DNS Entry:  https://blusky.blub0x.com

IP Address:  Redacted

Other:

HOT SITE SERVER

This is part of a dynamic pool that scales out on demand

APPLICATIONS

(Use bold for Hot Site)

BluSKY

ASSOCIATED SERVERS

N/A

 

KEY CONTACTS

 

Hardware Vendor

Microsoft Azure

System Owners

Microsoft

Database Owner

Engineering – Sean Dyer, Simon Goldshmid, Robert Domings, Vadim Ivantsevich

Application Owners

Engineering – Sean Dyer, Simon Goldshmid, Robert Domings, Vadim Ivantsevich

Software Vendors

Microsoft

Offsite Storage

Not Applicable

 

BACKUP STRATEGY for SYSTEM TWO

 

Daily

Azure Raw Storage

Monthly

Azure Raw Storage

Quarterly

Not Applicable – this is an application server,not a db.

 

SYSTEM TWO
DISASTER RECOVERY PROCEDURE

 

 

Scenario 1

 

Total Loss of Data

 

Not Applicable – see System 1 BluSKY Database

 

Scenario 2

 

Total Loss of HW

 

If the hardware fails, additional machines will automatically launch based on availability, CPU load and available RAM.  If the entire datacenter goes down, then fail over to West Coast Azure Website and rebuild East coast with either latest OS backup or re-deploy from Source Control.

 

 

ADDENDUM

 

CONTACTS

 

Sean Dyer

sdyer@blub0x.com
603-508-0447

Simon Goldshmid

sgoldshmid@blub0x.com
781-883-3284

Robert Domings

bbrown@blub0x.com

Vadim Ivantsevich

vindigo@blub0x.com

 

 

File Systems 12-01-2017

File System as of 12-01-2017

 

Minimal file systems to be created and restored from backup:

 

 

 

Filesystem            kbytes       Used       Avail       %used         Mounted on

 

IIS directory

Other critical files to modify

Not Applicable

Necessary directories to create

Not Applicable

Critical files to restore

Not Applicable

Secondary files to restore

Not Applicable

Other files to restore

Not Applicable

 

Disaster Recovery Plan for Voice Communications

 

SYSTEM
 

 

OVERVIEW

 

 EQUIPMENT

Provided as a service from Cricket

HOT SITE EQUIPMENT

Not applicable

SPECIAL APPLICATIONS

 

ASSOCIATED DEVICES

 

 

KEY CONTACTS

 

Hardware Vendor

Cricket

System Owners

Cricket

Database Owner

Not Applicable

Application Owners

Jesica Trejo

Software Vendors

Not Applicable

Offsite Storage

Not Applicable

Network Services

Not Applicable

 

BACKUP STRATEGY for Voice Communications

 

Daily

Not Applicable

Monthly

Not Applicable

Quarterly

Not Applicable

 

SYSTEM TWO
DISASTER RECOVERY PROCEDURE

 

 

Scenario 1

 

Total Loss of Switch

 

Not Applicable – provided as a service

 

Scenario 2

 

Total Loss of Network

 

Employees will use their cell phones until service is restored.  As an alternative to that, employees can also use Skype.

 

 

ADDENDUM

 

CONTACTS

 

Jesica Trejo

Jtrejo@blub0x.com

 

Disaster Recovery Plan for Email Communications

 

SYSTEM
 

 

OVERVIEW

 

  EQUIPMENT

Provided as a service from Microsoft Office 365

HOT SITE EQUIPMENT

Not applicable

SPECIAL APPLICATIONS

 

ASSOCIATED DEVICES

 

 

KEY CONTACTS

 

Hardware Vendor

Microsoft

System Owners

Microsoft

Database Owner

Not Applicable

Application Owners

Sean Dyer

Software Vendors

Not Applicable

Offsite Storage

Not Applicable

Network Services

Not Applicable

 

BACKUP STRATEGY for Voice Communications

 

Daily

Not Applicable

Monthly

Not Applicable

Quarterly

Not Applicable

 

SYSTEM TWO
DISASTER RECOVERY PROCEDURE

 

 

Scenario 1

 

Total Loss of Switch

 

Not Applicable – provided as a service

 

Scenario 2

 

Total Loss of Network

 

Employees can use the web interface (https://office365.com) if the email servers are still operational but there is an issue with the interface to the mail clients.  In the case of complete failure of Office365, employees will have to use Skype and voice comms as a temporary means of communication with one another internally.  Externally, individual employees can use personal email accounts if they do not include any proprietary information.  If Office365 is expected to be an extended issue, the company will change email providers and resume email service within 24-48 hours.

 

 

ADDENDUM

 

CONTACTS

 

Sean Dyer

sdyer@blub0x.com

Damage Assessment Form

 

Key Business

Process Affected

Description Of Problem

Extent Of Damage

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

_____________

 

Management of DR Activities Form

 

•      During the disaster recovery process all activities will be determined using a standard structure;

•      Where practical, this plan will need to be updated on a regular basis throughout the disaster recovery period;

•      All actions that occur during this phase will need to be recorded.

 

Activity Name:

Reference Number:

Brief Description:

 

 

 

Commencement

Date/Time

Completion

Date/Time

Resources Involved

In Charge

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

__________________

Disaster Recovery Event Recording Form

 

•      All key events that occur during the disaster recovery phase must be recorded.

•      An event log shall be maintained by the disaster recovery team leader.

•      This event log should be started at the commencement of the emergency and a copy of the log passed on to the business recovery team once the initial dangers have been controlled.

•       The following event log should be completed by the disaster recovery team leader to record all key events during disaster recovery, until such time as responsibility is handed over to the business recovery team. 

 

Description of Disaster:

Commencement Date:

Date/Time DR Team Mobilized:

 

Activities Undertaken by DR Team

Date and Time

Outcome

Follow-On Action Required

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Disaster Recovery Team's Work Completed: <Date>

Event Log Passed to Business Recovery Team: <Date>

 

_________________

 

Disaster Recovery Activity Report Form

 

•      On completion of the initial disaster recovery response the DRT leader should prepare a report on the activities undertaken.

•      The report should contain information on the emergency, who was notified and when, action taken by members of the DRT together with outcomes arising from those actions.

•      The report will also contain an assessment of the impact to normal business operations.

•      The report should be given to the business recovery team leader, with a copy to senior management, as appropriate.

•      A disaster recovery report will be prepared by the DRT leader on completion of the initial disaster recovery response.

•      In addition to the business recovery team leader, the report will be distributed to senior management

 

The report will include:

•      A description of the emergency or incident

•      Those people notified of the emergency (including dates)

•      Action taken by members of the DRT

•      Outcomes arising from actions taken

•      An assessment of the impact to normal business operations

•      Assessment of the effectiveness of the BCP and lessons learned

•      Lessons learned

__________

 

Mobilizing the Disaster Recovery Team Form

 

•      Following an emergency requiring recovery of technology infrastructure assets, the disaster recovery team should be notified of the situation and placed on standby.

•      The format shown below can be used for recording the activation of the DR team once the work of the damage assessment and emergency response teams has been completed.

 

Description of Emergency:

Date Occurred:

Date Work of Disaster Recovery Team Completed:

 

Name of Team Member

Contact Details

Contacted On (Time / Date)

By Whom

Response

Start Date Required

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Relevant Comments (e.g., Specific Instructions Issued)

 

 

___________

 

Mobilizing the Business Recovery Team Form

 

  • Following an emergency requiring activation of the disaster recovery team, the business recovery team should be notified of the situation and placed on standby.
  • The format shown below will be used for recording the activation of the business recovery team once the work of the disaster recovery team has been completed.

 

Description of Emergency:

Date Occurred:

Date Work of Business Recovery Team Completed:

 

Name of Team Member

Contact Details

Contacted On (Time / Date)

By Whom

Response

Start Date Required

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Relevant Comments (e.g., Specific Instructions Issued)

 

 

Monitoring Business Recovery Task Progress Form

 

•      The progress of technology and business recovery tasks must be closely monitored during this period of time.

•      Since difficulties experienced by one group could significantly affect other dependent tasks it is important to ensure that each task is adequately resourced and that the efforts required to restore normal business operations have not been underestimated.

 

Note: A priority sequence must be identified although, where possible, activities will be carried out simultaneously.

 

Recovery Tasks

(Order of Priority)

Person(s) Responsible

Completion Date

Milestones Identified

Other Relevant Information

Estimated

Actual

1.

 

 

 

 

 

2.

 

 

 

 

 

3.

 

 

 

 

 

4.

 

 

 

 

 

5.

 

 

 

 

 

6.

 

 

 

 

 

7.

 

 

 

 

 

 

 

 

 

 

 

 

___________

 

Preparing the Business Recovery Report Form

  • On completion of business recovery activities the BRT leader should prepare a report on the activities undertaken and completed.
  • The report should contain information on the disruptive event, who was notified and when, action taken by members of the BRT together with outcomes arising from those actions.
  • The report will also contain an assessment of the impact to normal business operations.
  • The report should be distributed to senior management, as appropriate.

 

The contents of the report shall include:

  • A description of the incident
  • People notified of the emergency (including dates)
  • Action taken by the business recovery team
  • Outcomes arising from actions taken
  • An assessment of the impact to normal business operations
  • Problems identified
  • Suggestions for enhancing the disaster recovery and/or business continuity plan
  • Lessons learned

 

Communications Form

 

  • It is very important during the disaster recovery and business recovery activities that all affected persons and organizations are kept properly informed.
  • The information given to all parties must be accurate and timely.
  • In particular, any estimate of the timing to return to normal working operations should be announced with care.
  • It is also very important that only authorized personnel deal with media queries.

 

 

Groups of Persons or Organizations Affected by Disruption

Persons Selected To Coordinate Communications

to Affected Persons / Organizations

Name

Position

Contact Details

Customers

 

 

 

Management & Staff

 

 

 

Suppliers

 

 

 

Media

 

 

 

Stakeholders

 

 

 

Others

 

 

 

 

Returning Recovered Business Operations to Business Unit Leadership

 

  • Once normal business operations have been restored it will be necessary to return the responsibility for specific operations to the appropriate business unit leader.
  • This process should be formalized in order to ensure that all parties understand the change in overall responsibility and the transition to business-as-usual.
  • It is likely that during the recovery process, overall responsibility may have been assigned to the business recovery process lead.
  • It is assumed that business unit management will be fully involved throughout the recovery, but in order for the recovery process to be fully effective, overall responsibility during the recovery period should probably be with a business recovery process team.

Business Process/Function Recovery Completion Form

 

The following transition form should be completed and signed by the business recovery team leader and the responsible business unit leader, for each process recovered.

A separate form should be used for each recovered business process.

 

Name Of Business Process

Completion Date of Work Provided by Business Recovery Team

 

Date of Transition Back to Business Unit Management

(If different than completion date)

 

 

I confirm that the work of the business recovery team has been completed in accordance with the disaster recovery plan for the above process, and that normal business operations have been effectively restored.

 

Business Recovery Team Leader Name: ________________________________________
 

Signature: ________________________________________________________________

 

Date: __________________________

 

(Any relevant comments by the BRT leader in connection with the return of this business process should be made here.)

 

 

 

 

 

I confirm that above business process is now acceptable for normal working conditions.

 

Name: ___________________________________________________________________

 

Title: ____________________________________________________________________

 

Signature: ________________________________________________________________

 

Date: __________________________

 

 

 

  • Was this article helpful?